Episode 1: The Inherited Monster Coach Ir. Wan, 01/05/202502/06/2025 “It started with a schedule that looked too good to be true. It always does.” 🏗️ Scene: Monday Morning | 9:03 AM A black coffee. A blinking cursor. And a file titled:“Project Phoenix – Baseline V1 (Approved).mpp” They told me it was “ready to go.”No need to build from scratch.“Just adjust the dates,” they said.“Reuse what worked on the warehouse job.” Warehouse?This was a residential development with underground parking and phased handovers. But hey—if it saves time, right? 🚩The Red Flags Day one, I noticed oddities: Activities starting mid-week with no logic links Float on foundations despite sequential dependencies And a strange milestone: “Mezzanine Slab Poured – Week 6” …except this project didn’t have a mezzanine. 🕵️‍♂️ I started digging.The durations? Same.WBS? Same.Calendars? Copied over—public holidays for another state. The worst part?They had already submitted this “baseline” to the client. 🧱 What Went Wrong? The original planner had built a solid plan—for a different job, site, scope, and structure. But instead of building new, someone hit Ctrl+C, Ctrl+V, slapped on a new project name, and replaced a few labels. They inherited a monster. Tasks were out of sequence Constraints didn’t match reality Key inspections were missing Procurement activities didn’t reflect new vendors or lead times The copy-and-paste job introduced invisible assumptions—like that access roads would be ready by Week 3. (Spoiler: they weren’t.) ⏳ The Fallout Rain season came.The excavation team waited for access that never came.The subcontractors stared at the schedule and shrugged: “This isn’t what we agreed to.” On paper, the progress looked fine.In reality, work was stalled for 14 days before anyone raised a flag. Senior management asked, “Why didn’t we foresee this?” We did.The schedule didn’t. 📌 The Lesson Never inherit a schedule without a forensic review.Copying a plan without full understanding is like performing surgery with someone else’s x-rays. ✅ Pro Tips for Schedulers: Start with a logic auditCheck for: orphan tasks invalid relationships milestones with no dependencies 🧼 Clean the WBSDelete irrelevant phases. Rebuild the structure to reflect this scope. 📆 Replace the calendarReset working days, holidays, and shifts to match current location and contract. 🧠Challenge the assumptionsWhat worked in Project A may fail in Project B. Context matters more than structure. 📝 Document everythingIf you do copy anything—log what was reused, what was rebuilt, and what was retired. wan 🕵️ Quote Board “Schedules don’t lie. Schedulers do (when they’re lazy).”— The Scheduler “A recycled plan without review isn’t efficiency. It’s sabotage.”— PMO Lead, post-mortem 📖 Coming Up Next: Episode 2: Ctrl+C, Ctrl+Blame“When a school project failed, the trail led back… to a hospital schedule.” The Scheduler Files