Episode 3: The Missing Milestone

Coach Ir. Wan, 02/06/202505/06/2025
“A project that finished ‘on time,’ but nothing was complete.”

🏗️ Scene: The Wrap-Up That Wasn’t

The site team celebrated. The tracker showed green. The milestone said “Project Complete.”

Except, it wasn’t.

When I visited the site, sub-contractors were still there. Finishing works continued. Handover documents were incomplete. The client hadn’t even moved in.

I asked the planner: “Why does the schedule say we’re done?”

He replied, “Because we reached the last activity.”

And just like that, the missing milestone mystery began.

🧩 The Reveal

The problem was subtle but critical: the final milestone was not logically connected to the rest of the work.

The schedule ended with “Final Inspection Completed” and then immediately declared “Project Complete.”

But in reality:

  • External works were delayed.
  • As-built documentation was ongoing.
  • Client training hadn’t started.
  • The building wasn’t ready for occupancy.

The planner had marked the milestone based on the last construction task—not project deliverables.

🔥 The Fallout

  • The client claimed handover was late—even though reports showed “on time.”
  • Extension of time requests were denied due to premature milestone dates.
  • Trust in the schedule eroded.
  • Post-project review flagged the milestone logic as a key failure.

📌 The Lesson

Milestones are only as good as their links.

A schedule without proper milestone logic is like a book missing its last chapter. You think the story’s over—but nothing’s resolved.

✅ Pro Tips for Schedulers:

  • Define completion clearly: What does “Project Complete” mean? List all conditions.
  • Connect milestone to scope: Use finish-to-start ties with documentation, testing, client approvals.
  • Walk the path: Trace the logic from first task to final milestone. Any disconnect is a red flag.
  • Separate construction vs. handover: Don’t treat them as the same.
  • Review with stakeholders: Make sure your milestone logic reflects reality.

🕵️ Quote Board

“Finishing the build isn’t finishing the project.”
— Commissioning Engineer”
“A milestone is not a guess. It’s a verdict.”
— Scheduler’s Golden Rule”

📚 Coming Up Next:

Episode 4: The Lag That Laid a Trap
“How a careless lag caused a six-week delay.”